Our Projects

ONLINE SUPPORT

Tel: +6695-073-6889 , +6699-481-8989
Email: admin@bluewhitesolution.com

โปรเจคงานบำรุงรักษา

Shutdown Prize of wood green energy power plant

Shutdown of the Prize of wood green energy power plant by Blue White Solutions and Services Co., Ltd. has proceeded as follows.

  1. Calibration Instruments 44 EA.
  2. PM ectrical cabinet LV MCC/MDB, MV Switch gear 6.3 kV, MV Switch gear 33 kV
  3. Manufacture and installation of DB moving floor cabinet
  4. Replace UPS battery size 26Ah, 100Ah, 150Ah
  5. Repair step grate structure, ready to dismantle Removing and replacing 735 Grate bars
  6. Removed and replaced.Mounting point of WIFI CCTV camera

Install electrical equipment control system for Rep.115kV KT3A by 115/33kV 50MVA Tie Tx, Yala 1 High Voltage Station

Install electrical equipment control system for Rep.115kV KT3A by 115/33kV 50MVA Tie Tx

Install 33kV 1/c no.35 sq.mm. XLPE cable and cable termination, EGAT Khlong Ngae High voltage substation

Prepare working area for install HDPE pipe and XLPE underground cable 33kV 1/c 35 sq.mm., Install ground grid, Install cable termination and Install control cable to control box

Improve 115kV equipment for power supply circuit 1 and circuit 2,High Voltage Substation Phuket 2

Improve 115kV equipment for power supply circuit 1 and circuit 2,High Voltage Substation  Phuket 2 

Removal and installation of 115kV C-Bank control system, High-voltage power station EGAT Hat Yai 2

Removal and installation of 115kV C-Bank control system

Install electrical equipment control system 500kV Bus Reactor, Bangsapan 2 High Voltage Station

Install electrical equipment control system 500kV Bus Reactor, Bangsapan 2 High Voltage Station